Skip to main content

◎ Arcade Cripple Creek Trail Update ◎

Sundance Natural Area Bridge Closure

The existing bridge and sections of the trail within Sundance will be closed beginning Thursday 9/7/23 to allow construction of the new, ADA compliant bridge.  The tentative schedule for the new bridge install and trail work is as follows:

9/7/23: Close existing bridge and begin bridge removal and excavation

9/15/23: Begin pile-driving for new abutments

10/6/23: Set new bridge in place

10/9/23: Pave trail connections to bridge, install lighting and all trail components

10/31/23: Open new bridge and trail

 

To learn more about Arcade Cripple Creek Trail,  click here